Real Projects. Real Results.
See how Right Check's precision HVAC design approach delivers measurable outcomes for homeowners, builders, and contractors.
Oversized System Correction — Phoenix, AZ
Challenge
A homeowner's 5-ton system was short cycling constantly. The original installer used rule-of-thumb sizing without a load calculation. Humidity was uncontrolled and energy bills were excessive.
Solution
Manual J analysis revealed the true load at 3 tons. We specified a properly sized variable-speed system and recommended targeted duct modifications to optimize airflow.
Outcome
30% reduction in energy costs. Humidity complaints eliminated. Room-to-room temperature variance reduced from 8°F to under 2°F.
Airflow Rebalancing — Austin, TX
Challenge
A builder's spec home had severe comfort complaints. Second-floor bedrooms were consistently 6–8°F warmer than the main level. The existing duct layout used undersized trunk lines.
Solution
Complete Manual D redesign with properly sized trunk lines, balanced run-outs, and corrected fitting selections. Added return air paths for second-floor bedrooms.
Outcome
Temperature variance reduced to under 2°F. System airflow increased by 15%. Passed re-inspection without issues.
Permit-Ready Package — Denver, CO
Challenge
Custom home builder needed a complete HVAC design package on a tight timeline for a 4,200 sq ft mountain residence with challenging architectural features.
Solution
Delivered a complete J + D + S package promptly, accounting for altitude adjustments, large window areas, and cathedral ceiling spaces.
Outcome
Permit-Ready Documentation provided. Contractor reported a seamless installation process. Builder added Right Check to their standard project workflow.
Mixed-Use Retail Space — Tampa, FL
Challenge
Architect needed HVAC design for a 6,000 sq ft mixed-use building with retail on the ground floor and offices above. Previous design conflicted with the architectural layout.
Solution
Manual N calculations with zone-by-zone analysis. Designed a multi-zone system that respected the architectural intent while meeting ventilation and comfort requirements.
Outcome
Code compliance verified. Tenant build-out completed on schedule. Building owner reported consistent comfort across all zones.
REScheck Compliance — Minneapolis, MN
Challenge
Builder's permit application was rejected due to missing energy code compliance documentation. Project was stalled waiting for REScheck report.
Solution
Completed REScheck analysis rapidly, identified two envelope areas that needed insulation upgrades to meet Minnesota's energy code requirements.
Outcome
Permit-Ready Documentation provided promptly. Builder avoided costly delays and incorporated the insulation upgrades during framing stage.